Question
A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. Working together they can do the work in
More Previous year papers Questions
- If the diameter of a hemisphere is 21 cm, then the curved surface area (in cm²) of the hemisphere is: Take
- In an examination, 92% of the students passed and 480 students failed. If so, how many students appeared in the examination?
- Two friends A and B started a business by investing RS1,50,000 and RS 2,50,000, respectively. They agreed to distribute their earnings in the same ratio of...
- The sides of a rectangle are in the ratio of 3 : 8 and its area is 1944 cm². What is its perimeter?
- If △ ABC is right angled at B, AB = 12 cm and ∠ CAB = 60°, determine the length of BC.
- Which of the options can replace the question mark (?) in the following equation?
- Find the amount (integral value only) if a sum of ₹6,500 is being borrowed at 10% interest per annum for 2 years if interest is compounded half-yearly.
- Find the smallest number that can be subtracted from 148109326 so that it becomes divisible by 8.
- If the perimeter of an isosceles right triangle is 8 (√ 2 +1) cm, then the length of the hypotenuse of the triangle is:
- In a 100-marks test, the average of marks scored by 50 students was found to be 65. Later on, it was discovered that a score of 88 was misread as 68. Find ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)