Question
Two inlet pipes M and N alone can fill a tank in 12
hours and 15 hours respectively and an outlet pipe P alone can empty the whole tank in 10 hours. First pipe M is opened for 4 hours, then pipe P is opened for 2 hours and rest of the tank is filled by pipe N. In what time will the tank be filled completely?Solution
Total capacity = 60 units (LCM of 12, 15 and 10) Efficiency of pipe M = 60/12 = 5 units/hr Efficiency of pipe N = 60/15 = 4 units/hr Efficiency of pipe P = 60/-10 = -6 units/hr Capacity of tank filled by pipe M in 4 hours = 5 Γ 4 = 20 units Capacity of tank emptied by pipe P in 2 hours = -6 Γ 2 = -12 units Capacity of tank left for pipe N = 60 β 20 β (-12) = 52 units Time taken by pipe N to fill the remaining tank = 52/4 = 13 hrs Total time taken = 4 + 2 + 13 = 19 hrs
Sufficient food-supply was arranged to last for 30 days for 250 soldiers. If 50 soldiers did not attend the camp, for how many extra days will the food-...
24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the sa...
How can we determine the value of x, given that (x+8) workers, working 9 hours a day, can finish 60% of a task in 12 days, and (x+2) workers, working 3 ...
12 men take 6 days to complete a piece of work. They worked for a period of 2 days. After that, they were joined by 4 more men. How many more days will ...
A and B together can do a piece of work in 15 days which B and C together can do in 20 days. After A has been working at it for 3 days and then by B for...
- βPβ takes 25 days to complete a piece of work. βQβ is 25% more efficient than βPβ. Find the time taken by them to complete 90% of the work toge...
βAβ and βBβ can do a piece of work in 10 days and 15 days, respectively. They started working together but βAβ left after 3 days. Find the t...
A, B and C can complete a work in 10, 20 and 15 days respectively. A left the work 3 days before the work was completed and B left 1 days after A had le...
- A contractor assigned 18 laborers to complete a task in 16 days. Unfortunately, 6 laborers left after 6 days. How many additional days will be required to ...
A, B, and C can complete a task individually in 45, 35, and 63 days respectively. They start working together, but A leaves 24 days before the work is c...