๐Ÿ“ข Too many exams? Donโ€™t know which one suits you best? Book Your Free Expert ๐Ÿ‘‰ call Now!

  • google app store apple app store
  • โœ–

      Question

      P and Q can finish a project in 10 days, while Q and R

      can finish it in 12 days. If R's efficiency is 50% more than Q's, how long will it take for P to complete the project by himself?
      A 12 days Correct Answer Incorrect Answer
      B 18 days Correct Answer Incorrect Answer
      C 15 days Correct Answer Incorrect Answer
      D 25 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Let the total work be LCM of 10 and 12 = 60 units. Number of units of work done by P and Q together in one day = 60 / 10 = 6 units. Number of units of work done by Q and R together in one day = 60 / 12 = 5 units. Let Qโ€™s daily work be โ€˜xโ€™ units. Then Rโ€™s daily work is โ€˜1.5xโ€™ units. So, 1.5x + x = 5 2.5x = 5 x = 5 / 2.5, x = 2 Work done by P alone in one day = 6 โ€“ 2 = 4 Required time taken by P alone to complete the work = 60 / 4 = 15 days

      Practice Next

      Relevant for Exams:

      ask-question