Question
A, B and C started a partnership with investment of Rs.
X - 1200, Rs. X and Rs. X + 1800. If profit of B is invested in a scheme at the rate of 18% for 5 yrs at SI, then the interest received [is Rs.3600. If the total profit in the partnership is Rs.4800 more than the double of the profit of B. Which of the following/s is/are true. i) Sum of investment of A and B is equal to C. ii) Value of X is multiple of 18. iii) A gets 18.75% of the total profit.Solution
Profit earned by B, 3600 = (x Γ 18 x 5)/100 X = (3600 x 100)/(18 x 5) = Rs. 4000 Given that, total profit in the partnership is Rs.4800 more than the double of the profit of B. Total profit = 4800 + 2 Γ 4000 = Rs. 12800 Now, x/(2x + 600) = 4000/8800 => x/(2x + 600) = 5/11 => 11x = 5(2x + 600) => 11x = 10x + 3000 => x = 3000 So, Investment of A = 3000 β 1200 = Rs. 1800 Investment of B = 3000 Investment of C = x + 1800 = 3000 + 1800 = Rs. 4800 Statement i: 1800 + 3000 = 4800 4800 = 4800 Statement i is true. Statement ii: x = 3000, which is not the multiple of 18. Statement iii: A = 1800/(1800 + 3000 + 4800) = 18/96 x 100 = 18.75%, which is true.
- A builder employed 12 workers to complete a job in 18 days. But after 8 days, 4 workers quit. How many more days will be required to complete the remaining...
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
Akhil and Nikhil together can complete a work in 12 days while Nikhil alone takes 18 days to complete 25% of the work. If the efficiency of Sachin is 20...
- If a group of 8 boys and 12 girls can complete a task in 40 days, and a team of 4 girls alone can finish the same task in 80 days, how long will it take fo...
P and Q individually can complete the work in 36 days and 54 days respectively. If the time taken by R alone to complete the work is 1.25 times the time...
15 men can do a work in 30 days. After 18 days of work, 5 more men were engaged to finish the work. The number of days required to complete the remainin...
A, B and C alone can complete a work in 30, 60 and 45 days respectively. All of them started working together but after 3 days from start A left the job...
Rahul is 50% more efficient than that of Ramu. If Ramu can complete the work in 20 days, then find the time taken by both of them to complete 50% of the...
βDβ and βEβ together can finish a task in 40 days, while βEβ and βFβ together can finish the same task in 30 days. βDβ and βEβ t...
5 men and 10 women can do some work in 3 days. If each man is 150% more efficient than a woman, then find the time taken by 9 men to finish the same wo...