Question
Cost price of wheat (per kg) of type 'A' and 'B' is Rs.
90 and Rs. 150 respectively. Both are mixed and sold at Rs. 180 per kg at a profit of 50%. Find the ratio in which wheat of type 'B' is mixed with wheat of type 'A'.Solution
Cost price of mixture = (180 / 1.5) = Rs. 120
Let 'm' kg and 'n' kg of wheat of type 'A' and 'B' respectively be mixed.
So, (90m + 150n) ÷ (m + n) = 120
Or, 90m + 150n = 120m + 120n
Or, 30n = 30m
Or, m:n = 1:1
Lata can do 1/3rd of a work in 4 days and Asha can do 1/6th of the same work in 3 days. If both work together then how many days...
Asmita and Bhanu working together can complete the task in ____ days, and the efficiency of Sam is 50% more than that of Asmita. Bhanu alone can complet...
- 12 men working for 6 hours a day can complete a work in 20 days. If 30 women are employed to work, then find how many hours a day they have to work to comp...
A and B can complete a task together in 8 days, while B alone takes 16 days to finish it. A began working alone and left after ‘x’ days, after which...
Binny is 20% more efficient than Ankush, while Ankush is 50% more efficient than Raju. If the three of them—Ankush, Binny, and ...
A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 25 days. Find the time taken by B to compl...
A can complete a work in 18 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 50% of the w...
Arjun, Bharat and Chintu together can complete a task in 8 days. Bharat is 25% less efficient than Arjun. Arjun and Chintu together can complete the tas...
A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to w...
25 men and 45 women can complete a piece of work in 15 days, while 15 men and 60 women can complete it in 20 days. In how many days can 69 men and 67 wo...