Question
A solution is formed by mixing three liquids P, Q, and R
in the ratio 4:3:2. Liquid P contains 50% alcohol, Liquid Q contains 40% alcohol, and Liquid R contains 30% alcohol. What is the percentage of alcohol in the final mixture?Solution
Let the volumes of P, Q, and R be 4x, 3x, and 2x liters respectively. Total volume = 4x + 3x + 2x = 9x liters Alcohol in P = 4x Γ 0.50 = 2.00x liters Alcohol in Q = 3x Γ 0.40 = 1.20x liters Alcohol in R = 2x Γ 0.30 = 0.60x liters Total alcohol = 2.00x + 1.20x + 0.60x = 3.80x liters Percentage of alcohol = (3.80x / 9x) Γ 100 = 42.22% The percentage of alcohol in the final mixture is approximately 42%. Correct Option: d
βRβ and βSβ together can finish a work in 25 days. If βRβ increases his efficiency by 60% and βSβ decreases his efficiency by 20%, then...
A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to w...
A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio...
4 girls can do work in 8 days, 3 boys can do the same work in 9 days, 7 men in 2 days, and 5 women in 4 days. Who is the least efficient?
- A man can complete a job alone in 20 days. A woman can complete half of the same job in 15 days. If both work together, how many days will it take them to ...
A and B can finish a piece of work in 20 days and 30 days respectively. Both work on alternate days. In how many days will the work be completed when A ...
Arjun is 50% less efficient than the combined efficiency of Bheem and Cherry. If Bheem can complete a task in 12 days and Cherry in 20 days, determine t...
'Asmita,' who is three times as efficient as 'Bittu,' can complete a task on her own in 15 days. 'Asmita' and 'Bittu' began working together, but after ...
A can fabricate a divider in 23 days , while B alone can assemble it in 26 days, If they construct it together and get an installment of Rs 9800, then f...
- 18 workers can complete 9 tasks in 24 hours. Find the time required by 12 workers to finish 15 tasks.