Question
In a partnership business of A, B and C, what profit did
B get at the end of 2 years? I. A and B started the business by the investing in ratio 2:3. II. C joined after 8 months with Rs 5 lakhs III. After two years. A’s share in profit was Rs 40,000 In each of the following questions, a question and three statements I, II and III are given. You have to decide whether the date given in the statements are sufficient to answer the question or not.Solution
From statements I and III, since we know the investment ratio of A and B, we can get the share of B in the profit.
Thirty men working 8 hours daily complete a task in 16 days. If the work increases to three times the original and needs to be fi...
A can complete a piece of work in 12 days and B can complete the same work in 18 days. They work together for 4 days and then leave the remaining work ...
Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion ...
6 women and 4 children can complete a piece of work in 12 days. If 3 more women join them, they can finish 3/5 of the work in 6 days. Find the time take...
16 men can complete a work in 10 days. 10 men started the same work and left after working for βyβ days. The remaining work is completed by 6 men in...
'R' can independently complete a task in 36 days, whereas 'S' can accomplish 40% of the same work within 16 days. 'S' starts the task solo and withdraws...
A and B together can complete a piece of work in 32 days while A alone can complete 40% of the work in 32 days. Find the time taken by B to compl...
A can finish a task by himself in 25 days, whereas B can finish the same task by himself in 10 days. A begins the task but stops after 5 days, at which ...
βPβ alone can paint a house in 18 days, while βPβ and βQβ together can do it in 12 days. If βQβ started the work and left after 6 days, ...
βAβ can do a piece of work in 12 days. βBβ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.154...