Question
The average height of a group of 30 players was recorded as
168 cm. Later it was discovered that 172 was wrongly written as 182 and 160 was written as 150. What is the correct average height?Solution
ATQ,
Correct average
= {(30 Γ 168) β 182 + 172 β 150 + 160} / 30
= {5040 β 182 + 172 β 150 + 160} / 30
= {5040 β 182 + 172 β 150 + 160} / 30
= (5040 β 182 + 172 β 150 + 160) / 30
= 5040 β 182 + 172 = 5030 β 5030 β 150 + 160 = 5040
Correct average = 5040 / 30 = 168 cm
A, B and C alone can complete a work in 18, 32 and 24 days respectively. All of them started working together but after 3 days from start A left the job...
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed b...
Team A can built a project in 6 hours less than the time taken by Team B to built the same project.
The ratio of the strength of Team A to that o...
A group of 24 men is capable of finishing a task in 15 days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additiona...
A is capable of finishing a task in 60 days. B requires 40% more time than A to finish the same task. How many days will A and B need to complete 80% of...
Vijay can do a piece of work in 16 days and Sanjay can do the same work in 24 days. If Vijay works for 6 days and got Rs. 2700, and the remaining work w...
A and B can complete a work in 12 days and 16 days, respectively. They start working together, but after 4 days, A leaves the work. C joins B, and they ...
If a group of 20 boys and 10 girls can finish a task in 50 days, and a team of 8 girls alone can complete the same task in 120 days, how long will it ta...
'A' and 'B' can together complete a job in 15 days. If 'B' alone can finish 50% of the job in 20 days, how long would it take 'A' alone to complete the ...
βAβ and βBβ can complete a certain work in 10 days and 15 days, respectively. They started working together and worked till completion of the wo...