Question

28 men and 21 women can complete a work in 16 days. All of them start working together and after working for 12 days the women stopped working. All men alone complete the remaining work in 8 days. How many days will it take for completing the entire work if only 21 women are employed on the job?

A 15
B 32
C 20
D 40
E None of these
Practice Next

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)