Question
28 men and 21 women can complete a work in 16 days. All of them start working together and after working for 12 days the women stopped working. All men alone complete the remaining work in 8 days. How many days will it take for completing the entire work if only 21 women are employed on the job?
More Approximation Questions
- 5.25 x 4.09 + 3.99 x 9.67 + 6.01 x 14.88 = ?
- 14.232 + 19.98% of 629.99 = ? × 6.99
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.) ...
- What approximate value will replace the question mark (?) in the following? 9.89% of 999.5 = 14.95% of ?
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.) ?...
- What approximate value should come in the place of question mark in the following questions? (6.4% of 3125) + (14.9% of 503) = ?
- [34.01 × 18.98 – 12 × √576.03 – 198] ÷ 3.95 = ?
- (74.93% of 640.11 + 3/4 of 359.79)² - (1/3 of 80.87 × 2)² = ?
- ?% of (150.31 ÷ 14.97 × 50.011) = 319.98
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.) ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)