Question
A, B, and C can complete a piece of work separately in
10, 20 and 40 days, respectively. In how many days will the work be completed if A is assisted by both B and C every third day?Solution
A B C 10 20 40 40 Total work 4 2 1 Efiici The work of first 3 days =4+4+(4+2+1) =15units Similarly, the Next 3 days work=15units After 6days remaining work =40-(15+15) =10units 7days by A=4unit 8days by A=4units 9 days by A, B, C=2/7 Total days=8+2/7=58/7days.
What is the name of the think-tank proposed by Gujarat, similar to NITI Aayog?
What digital platform launched by the Government of India enables self-assessment for PDS depots?
Punjab National Bank recently inaugurated its first startup-centric branch in which city?
Why did New Zealand grant legal personhood to Mount Taranaki (TeKāhui Tupua) in February 2025?
How does the partnership between PNB MetLife and India Post Payments Bank (IPPB) aim to enhance life insurance accessibility?
On which date is Constitution Day commemorated?
According to WHO’s Mental Health Atlas 2024, what share of global suicides occurs in low- and middle-income countries?
What percentage growth in remittances was recorded in August 2024 under the Liberalised Remittance Scheme (LRS) compared to July 2024?
What is the key focus of Clause 6 of the Assam Accord, which was discussed between the Assam government and AASU?
What is a key finding of the SIDBI MSME Outlook Survey’s third edition?