Question
A, B, and C can complete a piece of work separately in
10, 20 and 40 days, respectively. In how many days will the work be completed if A is assisted by both B and C every third day?Solution
AÂ Â Â Â Â Â Â Â Â Â Â Â BÂ Â Â Â Â Â Â Â Â Â Â Â C 10Â Â Â Â Â Â Â Â Â Â 20Â Â Â Â Â Â Â Â Â Â 40 Â Â Â Â Â Â Â Â Â Â Â Â Â Â 40Â Â Â Â Â Â Â Â Â Â Total work 4Â Â Â Â Â Â Â Â Â Â Â Â 2Â Â Â Â Â Â Â Â Â Â Â Â 1Â Â Â Â Â Â Â Â Â Â Â Â Efiici The work of first 3 days =4+4+(4+2+1) =15units Similarly, the Next 3 days work=15units After 6days remaining work =40-(15+15) =10units 7days by A=4unit 8days by A=4units 9 days by A, B, C=2/7 Total days=8+2/7=58/7days.
HEAD AND SHOULDERS ABOVE
I) The new model is head and shoulders above its competitors in terms of both quality and design.
II) His perfo...
Charley Horse
- Think on your ______ Â
Select the most appropriate option to substitute the bold segment in the given sentence. If there is no need to substitute, select no improvement
make full use of and derive benefit from a resource
Can't cut the mustard
In the given question a sentence with a blank is given. From the options choose the idiom which will fit perfectly in the blank and make the sentence c...
Weather the storm
The traffic came to a standstill after the heavy downpour of rain.
Nip It in the Bud