Question
A, B, and C can complete a piece of work separately in
10, 20 and 40 days, respectively. In how many days will the work be completed if A is assisted by both B and C every third day?Solution
A B C 10 20 40 40 Total work 4 2 1 Efiici The work of first 3 days =4+4+(4+2+1) =15units Similarly, the Next 3 days work=15units After 6days remaining work =40-(15+15) =10units 7days by A=4unit 8days by A=4units 9 days by A, B, C=2/7 Total days=8+2/7=58/7days.
Recently the European Commission approved Bavarian Nordic's Imvanex vaccine for use against Monkeypox in EU. It is generally used for the treatment of__...
In which historical event did the British government for the first time acknowledge the demand for a Constituent Assembly in India?
Under the CETA, what percentage of Indian imports will the UK eliminate tariffs on?
What was the average technical efficiency of Public Sector Banks (PSBs) from FY06 to FY23?
Match the following list I and list II.
Consider the following statements regarding instruments of Monetary Policy:
I. The Repo rate is the interest rate at which the Reserve Bank provi...
Who is the author of the book “The India Way: Strategies for an Uncertain World”?
In which of the following states is the Bhitarkanika National Park situated?
Which rating agency predicts that by 2030, India will secure the position of the world's third-largest economy?
On 07 August 2025 in New Delhi, declassified versions of which joint doctrines were released by the CDS?