Question
A, B, and C can complete a piece of work separately in
10, 20 and 40 days, respectively. In how many days will the work be completed if A is assisted by both B and C every third day?Solution
AÂ Â Â Â Â Â Â Â Â Â Â Â BÂ Â Â Â Â Â Â Â Â Â Â Â C 10Â Â Â Â Â Â Â Â Â Â 20Â Â Â Â Â Â Â Â Â Â 40 Â Â Â Â Â Â Â Â Â Â Â Â Â Â 40Â Â Â Â Â Â Â Â Â Â Total work 4Â Â Â Â Â Â Â Â Â Â Â Â 2Â Â Â Â Â Â Â Â Â Â Â Â 1Â Â Â Â Â Â Â Â Â Â Â Â Efiici The work of first 3 days =4+4+(4+2+1) =15units Similarly, the Next 3 days work=15units After 6days remaining work =40-(15+15) =10units 7days by A=4unit 8days by A=4units 9 days by A, B, C=2/7 Total days=8+2/7=58/7days.
Which of the following Laptop is kept just below the brand which has 18 months warranty period? Also, what is the warranty period for that brand?
...Which of the following likes Yellow?
Which of the following movies does Kunal like?
How many persons have positions between G and D?
Choose the correct water image of the given figure (X) from amongst the four alternatives. Â
Read the directions carefully and answer the following questions.
Seven persons O, P, Q, R, S, T, and U live in six floored building but not ne...
Who among the following person likes Black?
Who lives immediately above T?
How many floor between W and the one who likes REEBOK?
Which of the following is true regarding box P?