Question
A, B, and C can complete a piece of work separately in 10, 20 and 40 days, respectively. In how many days will the work be completed if A is assisted by both B and C every third day?
More Approximation Questions
- 19.912 - (599.98 - 96.01 ÷ 3.01) ÷ 1.98 = ? + √254
- (4096)1/3 × 10.11 × 11.97 ÷ 24.32 = ? + 15.022
- What approximate value will replace the question mark (?) in the following? √484.01 + √? – ³√1000.99 = √400.08
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.) ...
- A regular hexagon has a side length of 8 units. What is the area of the half of the hexagon?
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exactvalue.) ...
- ? = 49.97% of 38.09% of 1998.95
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.)
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.)(7....
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.)
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt