Question

When must the buyer make payment to the supplier for goods or services rendered under the MSMED Act?

A Within thirty days from the day of acceptance or deemed acceptance
B Within sixty days from the day of acceptance or deemed acceptance
C On or before the date agreed upon between the buyer and the supplier, not exceeding forty-five days from the day of acceptance or deemed acceptance
D On or before the appointed day, regardless of any agreement between the buyer and the supplier
Practice Next