Question
Under the Prevention of Money -Laundering Act, 2002 any
record which has been seized or frozen and the Investigating Officer or any other officer authorised by the Director in this behalf has reason to believe that any of such records are required to be retained for any inquiry under the Act then such records may if seized, be retained or if frozen, may continue to remain frozen, for a period of ________________Solution
Section 21 Retention of records- —(1) Where any records have been seized, under section 17 or section 18 or frozen under sub-section (1A) of section 17 and the Investigating Officer or any other officer authorised by the Director in this behalf has reason to believe that any of such records are required to be retained for any inquiry under this Act, such records may if seized, be retained or if frozen, may continue to remain frozen, for a period not exceeding one hundred and eighty days from the day on which such records were seized or frozen, as the case may be.
Rohit is five times as efficient as Sohan and twice as efficient as Mohan. If Sohan takes 15 days to finish some work, then find the time taken by Rohit...
- C is 37.5% more efficient than A, and A is 60% more efficient than B. If A, B, and C together can complete a task in 40 days, how long will it take A alone...
Thirty men working 8 hours daily complete a task in 16 days. If the work increases to three times the original and needs to be fi...
Ajay started a work and left working after 8 days. Vijay finished the remaining work in next 36 days. Had Ajay left the work after working for 12 days t...
45 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for ...
20 men can do a task in 18 days while 30 women can complete the same task in 24 days. In how many days will 1 man and 1 woman complete it together?
Mohan, Sohan, and Rohan alone can finish a piece of work in 50, 100, and 150 days respectively. They start the work together, but Mohan leaves after 8 d...
A certain number of women can complete a piece of work in 9 days. If there were 18 women less, it would take 6 days more to complete the same work. If (...
A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can ...
- Ayaan and Kabir started working together on a task. Ayaan does 4 units per day and Kabir can finish the full task in 25 days alone. The total work is 100 u...