Start learning 50% faster. Sign in now
Ans. b, As per Code 50. (1) When a contractor receives work order from an establishment either to supply contract labour in the establishment or to execute the contract through contract labour in the establishment he shall, within such time and in such manner as may be prescribed, intimate to the authority referred to in section 119. (2) Where the contractor fails to give intimation under sub-section (1), the designated authority may, after giving the holder of the licence an opportunity of showing cause, suspend or cancel the licence in such manner as may be prescribed by the appropriate Government.
A and B can complete a task together in 18 days, while B alone takes 36 days to finish it. A began working alone and left after ‘x’ days, after whic...
Ajay alone can complete a work in 10 days and Bittu alone can complete the same work in 15 days. Ajay starts the work alone and after three days Bittu j...
10 men or 50 women can complete a piece of work in 40 days. A man and a woman together complete the work and receive a total wage of Rs. 6,000. Find the...
Ram can do a piece of work in 50 days. He alone worked at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, t...
'Sumit' can complete (3/8) of a job in 24 days, where as 'Sumit' and 'Tarun' together can finish it in 16 days. Calculate the time 'Tarun' needs to comp...
P and Q can do a piece of work in 32 and 40 days respectively. They began to work together but P leaves after sometimes and Q completed remaining work i...
Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish t...
A and B can complete a work together in 24 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...
Calculate the number of days it would take for a team of 8 boys, 5 girls, and 5 children to Construct a building. This building was previously constru...
‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the ...