Question

Using the Basic COCOMO model for an organic-mode project with an estimated size of 32 KLOC (thousand lines of code), what is the estimated effort in person-months? 

A ~76.8 PM
B ~124.6 PM
C ~91.3 PM
D ~48.5 PM
E ~32 PM