Question

Four processes arrive as follows: P1 (arrival 0, burst 8), P2 (arrival 1, burst 4), P3 (arrival 2, burst 9), P4 (arrival 3, burst 5). Using preemptive Shortest Remaining Time First (SRT

  • F scheduling, what is the average waiting time across all four processes?
A 5.50 milliseconds
B 6.00 milliseconds
C 7.25 milliseconds
D 6.50 milliseconds
E 8.25 milliseconds