Question

In project management, the critical path in a PERT chart represents:

A The shortest path to complete the project.
B The sequence of tasks with no dependencies.
C The sequence of tasks that determines the project's duration.
D The list of tasks that can be delayed without affecting the project timeline.
E The path with the maximum slack.
Practice Next

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)