Question
Consider the following statement about earthquake
– I) Intensity of earthquakes is measured on the Mercalli Scale. II) Magnitude of earthquake depends directly upon Amplitude of an earthquake wave. III) Every integer on Richter Scale shows a 50 times increase in energy released Which of the statements are true?Solution
The intensity of an earthquake is measured on two scales (i) Richter scale (ii) Mercalli scale. The intensity of an earthquake is the measurement of energy released. The Richter scale has a shaking amplitude 10 times that of the previous integer and shows an increase of 32 times in energy. Energy equal to 6 ounces of TNT is released by an earthquake of a magnitude of 1.Â
A and B can complete a task together in 18 days, while B alone takes 36 days to finish it. A began working alone and left after ‘x’ days, after whic...
30 workers working 8 hours daily can finish a job in 20 days. Find the time needed by 20 workers working 12 hours daily to finish the same job.
A, B and C can mow a field in 36 days, 72 days and 54 days respectively. All the three began the work together on January 1, 2016, but A left 8 days and...
20 men can complete a piece of work in 40 days. ‘x’ men started the work and after 35 days 64 more men joined them so that whole work was finished i...
'P' and 'Q' can finish a piece of work in 45 days and 90 days, respectively. 'P' starts working alone, and 'Q' joins after 'r' da...
Krishna can do a piece of work in 25 days. He alone worked at it for 10 days and then Balram completed alone the rest work in 20 days. In how many days,...
A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of e...
Time taken by 'X' and 'Y' to complete a work alone is 72 days and 120 days respectively. Find the time taken by 'X' and 'Y' together to complete 25% of ...
A buffalo alone can plough field ‘A’ in 50 days. A Bull alone can plough the field ‘A’ in 75 days. Find the number of days taken by 1 bulls and ...
Arjun can finish 60% of a job in 9 days. Bittu needs 9 more days than Arjun to finish the whole job, and Bittu’s efficiency is 25% higher than Charu�...