Anita and Binita have individual completion times for a task; Anita can complete it in 40 days, while Binita can do it in 56 days. Anita initiated the t...
12 children and 18 men complete an artwork in 9 days. Each child takes twice as long as a man to finish the artwork. How many days will it take for 18 m...
A group of 24 men is capable of finishing a task in 15 days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additiona...
- Rohit and Mohit began a job together, but after 10 days Rohit left the task. Mohit finished the rest of the job alone in 8 days. Rohit is 40% less efficien...
A and B together can complete a piece of work in 12 days, while B and C can complete it in 15 days. A, B, and C together can complete the same work in 8...
Rohan can finish a task alone in 24 days. Shreya can do 50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% ...
A and B together can complete a work in 20 days. After working together for 8 days, B leaves, and A completes the remaining work in 16 more days. In how...
A certain Sales target was assigned to a team of men to complete in 18 days. But 8 men did not turn up for the target and the rest men complete the sale...
Karan, Arjun and Krunal alone can complete a work in 50, 75 and 60 days respectively. All of them started working together but after 9 days from start K...
35 men can complete a piece of work in 40 days. ‘x’ men started the work and after 30 days 60 more men joined them so that whole work was finished i...