Question
What is the purpose of the PM Kisan scheme in
India?Solution
The Pradhan Mantri Kisan Samman Nidhi (PM-KISAN), a Central Sector Scheme, aims at providing financial assistance to all cultivable landholding farmer families across the country, subject to certain exclusion criteria.
A completes 1/3 of a task in 4 days, while B finishes the remaining work in 8 days. If B is 25% less efficient than C, how many days will A, B, and C to...
X men can complete the piece of work in 45 days and (X + 46) men can complete the same work in 23 days less than that of days taken by X men. Find the v...
Anuj can complete a certain piece of work in 25 days by taking rest for 9 hours daily. If he rests twice as much as before and also works twice as fast...
A2 type βPβ pipes can fill a tank in 350 hours, while B2 type βQβ pipes can fill the same tank in 504 hours. (10A Γ 6B) t...
Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' ...
‘A’ and ‘B’ together can complete a work in 10 days, while ‘B’ and ‘C’ together can complete the work in...
A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. In how many days, total work will be comple...
Akhil and Nikhil together can complete a work in 12 days while Nikhil alone takes 18 days to complete 25% of the work. If the efficiency of Sachin is 20...
βAβ and βBβ can complete a certain work in 15 days and 10 days, respectively. They started working together and worked till completion of the wo...
A man, a woman and a girl can together complete a piece of work in 60 days. If 10 men can do it in 16 days and 8 girls can finish it in 30 days, how lon...