As per the information given below, the correct answer is option C. India and Canada have agreed to work on taking the defence relationship to the next level and make defence an important pillar of bilateral relationship. Defence Minister Rajnath Singh today held telephonic conversation with his Canadian counterpart Anita Anand. The two leaders discussed ways to develop bilateral defence relations, which will be reflective of their democratic ethos and a shared interest in the peace and security of the Indo-Pacific. Mr. Singh welcomed the increased Canadian naval presence in the Indo-Pacific. Both Ministers also discussed potential areas of defence cooperation from UN peacekeeping training to defence-industrial cooperation. Mr Singh highlighted India as an attractive defence manufacturing destination with competitive land and labour costs and two defence industrial corridors. He also invited Canadian defence companies to invest in India and carry out co-production. Ms Anita Anand briefed him about Canada’s Indo-Pacific Strategy and the importance attached to enhancing engagement with India.
Armaan and Bhanu working together can finish a certain task in 90 days, and Bhanu collaborating with Chintu can complete the same task in 70 days. If Ar...
Two individuals, P and Q, can complete a task in (x + 6) days and (x + 3) days, respectively. Another individual, S, is capable of completing 25% of the...
The efficiency of A, B, C, D are in the ratio of 6 : 5 : 4 : 3. If A and C can do a work together in 6 days. Then How much days B and D will take to com...
'A' requires 16 more days to finish a task compared to 'B'. When 'A' and 'B' collaborate, they complete the task in 9 days fewer than 'B' would need to ...
When working alone, Ansh takes 12 more days than time taken by Ansh and Balu together to finish certain work. If Ansh is 50% more efficient than Balu, t...
Virat can do a piece of work in 26 days and Sachin can do the same work in 39 days. If Virat works for 5 days and got Rs. 3000, and the remaining work w...
A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to w...
40 men can complete a piece of work in 48 days. ‘x’ men started the work and after 33 days 64 more men joined them so that whole work was finished i...
A group of 21 boys, each working 6 hours a day, complete a school project in 15 days. How many days will it take for 18 boys, wor...
- Priya can solve 30 questions in 1.5 hours. If she decreased her efficiency by 25%, then how much time would she take to solve the same number of questions?