The United Nations Development Programme (UNDP) has highlighted significant multidimensional vulnerability in the Northern and Eastern regions of Sri Lanka, with a particular focus on the substantial portion of the population living below the poverty line. This finding draws attention to the complex challenges faced by these communities, including economic hardship, limited access to basic services, and the need for sustainable development efforts to improve living conditions and opportunities for those affected.
Anil and Ashish receive Rs.1400 for work of 7 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
A can complete a certain work in 12 days, while B can complete it in 15 days. After working together for 4 days, A leaves and B continues working alone....
'A' alone can do some work in 15 days. 'B' is 40% more efficient than 'A'. 'A' worked alone for 8 days and left. How much time (in days) does 'B' need t...
Four boys and nine girls can complete a task in 24 days. Three boys and five girls can finish the same task in 36 days. How many ...
Peter and Rachel can complete a project together in 20 days. Peter takes four times as long as Rachel to complete the same project alone. Find the time ...
'Manoj' can complete some work alone in 40 days. 'Sohan' is twice as efficient as 'Rohan' and five times as efficient as 'Manoj'. If 'Manoj' and 'Rohan'...
Efficiency of A is 25% more than B and B takes 30 days to complete a piece of work. A started the work alone and then B joined him 4 days before actual ...
A alone can complete 60% of a work in 36 days while B takes 30 days more than A to complete it. If B and C together can complete the work in 40 days, th...
- Karan can do 60% of a job in 36 days while Meena does 20% in 18 days. Karan works for 20 days and stops. Calculate how many days Meena will take to complet...
6 men and 10 boys can finish a task in 18 days. If each boy is between 1/3rd to equal the efficiency of a man, find the maximum and minimum number of da...