The eighth India International Science Festival is to be held in Bhopal. The Union Minister Jitendra Singh inaugurated the festival. According to the Government of India, the festival is a step in moving towards “AMRIT KAAL” Theme : Marching Towards AMRIT KAAL with Science and Technology.
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
Deepak and Deepti with each other can complete a work in 60 days, Deepti and Danny in 90 days and Deepak and Danny in 90 days. In how many days can De...
Workers A, B, and C can individually complete a task in 35 days, 20 days, and 28 days, respectively. If B and C work together for a certain number of d...
‘A’ can complete a work in 18 days and is 10% more efficient than ‘B’. ‘A’ and ‘B’ start the work together, but ‘A’ leaves after 15 ...
Vijay can do a piece of work in 34 days and Sanjay can do the same work in 51 days. If Vijay works for 5 days and got Rs. 1650, and the remaining work w...
A and B can complete a work together in 18 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed b...
'B' is 20% more efficient than 'A.' 'A' began working on a task alone and continued for 8 days, after which 'B' took over and completed the remaining wo...
‘P’ and ‘Q’ can complete a project in 45 days and 60 days respectively while ‘P’, ‘Q’ and ‘R’ together can complete the same project...
A can do a work in 45 days and the same the work is done in 15 days by A and B together, then in how many days B can complete the 20% of work?
The efficiency of P, Q, R, S are in the ratio of 6:5:4:3. If P and R can do a work together in 6 days. Then How many days Q and S will take to complete ...