Question
Consider the following statements: 1. The average
population density of India is between 600-700 persons per square kilometer. 2. 2002-2007 is the duration of the Tenth Five-Year Plan. 3. Installed electricity generation capacity in India is in excess of 2 lakh Megawatt. Which of the statements given above is/are correct?Solution
β’ As per the latest Data of the government for July 2022, Total Installed electricity generation of India is 4,03,760 MW. β’ Tenth Five Year Plan was implemented during the duration of 2002-2007 with following targets: o Attain 8% GDP growth per year. o Reduction of poverty rate by 5% by 2007. o Providing gainful and high-quality employment at least to the addition to the labour force. o Reduction in gender gaps in literacy and wage rates by at least 50% by 2007. o 20-point program was introduced. o Target growth: 8.1% β growth achieved: 7.7%. o The Tenth Plan was expected to follow a regional approach rather than sectoral approach to bring down regional inequalities. Expenditure of βΉ43,825 crore (US$5.5 billion) for tenth five years.
Thirty men working 8 hours daily complete a task in 16 days. If the work increases to three times the original and needs to be fi...
A can complete a piece of work in 12 days and B can complete the same work in 18 days. They work together for 4 days and then leave the remaining work ...
Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion ...
6 women and 4 children can complete a piece of work in 12 days. If 3 more women join them, they can finish 3/5 of the work in 6 days. Find the time take...
16 men can complete a work in 10 days. 10 men started the same work and left after working for βyβ days. The remaining work is completed by 6 men in...
'R' can independently complete a task in 36 days, whereas 'S' can accomplish 40% of the same work within 16 days. 'S' starts the task solo and withdraws...
A and B together can complete a piece of work in 32 days while A alone can complete 40% of the work in 32 days. Find the time taken by B to compl...
A can finish a task by himself in 25 days, whereas B can finish the same task by himself in 10 days. A begins the task but stops after 5 days, at which ...
βPβ alone can paint a house in 18 days, while βPβ and βQβ together can do it in 12 days. If βQβ started the work and left after 6 days, ...
βAβ can do a piece of work in 12 days. βBβ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.154...