Question
30 men can complete a piece of work in 48 days. โxโ
men started the work and after 33 days 64 more men joined them so that whole work was finished in the desired time. Find the value of โxโSolution
Total work = 30 ร 48 = 1440 units According to question; 33 ร x + 15 ร (x + 64) = 1440 Or, 33x + 15x + 960 = 1440 Or, 48x = 480 Or, x = 10
What unique feature does Axis Bank's NFC Soundbox, developed in collaboration with Mastercard, offer for transactions exceeding Rs 5000?
How many titles has Iga Swiatek won at the WTA 1000 level after her recent victory at the Madrid Open?
The Indian Navyโs Submarine Rescue Unit participated in Exercise Pacific Reach (XPR-25) hosted by which country?
Which country highest civilian award has been bestowed upon on Sri Ravi Shankar ?
Which company received final approval from the RBI to operate as an online payment aggregator in India?
Department of Posts under Ministry of Communications has launched an โOnline request Transfer Portalโ for _____.
Which platform is used in the pact between PhonePe and SIDBI to enable registration of informal micro enterprises?
Consider the following about Pradhan Mantri MUDRA Yojana (PMMY):
I. It is a scheme launched in 2014 for providing loans.
II. It providing ...
What is the focus of the Pradhan Mantri Awas Yojana โ Urban (PMAY-U)?
How many ex-servicemen are planned to be involved in Maharashtra's school military education initiative?