30 men can complete a piece of work in 48 days. ‘x’ men started the work and after 33 days 64 more men joined them so that whole work was finished in the desired time. Find the value of ‘x’
More ESIC Part B Questions
- The value of logtan1° + logtan2° +....+logtan89° is:
- Select the set in which the numbers are related in the same way as are the numbers of the following sets. (NOTE: Operations should be performed on the who...
- Which of the following is/are Fundamental duty/duties incorporated in the constitution of India by the 42nd constitutional amendment act? 1. To value and...
- If in a population the natality is 50 and mortality is 80, in a span of 10 years. What is the growth rate (GR) of that population?
- If each vowel in the word CONSTRUCTION is changed to the letter following it in the English alphabetical order and each consonant is changed to the letter ...
- Which among the following are the functions of Money? a) Unit of value b) Standard for deferred payment c) Store of value d) Medium of exchange
- Question 7
- When a number is increased by 30% then the number obtained is 34 less than thrice the original number. Find the original number.
- Under the Constitution of India, the safety, welfare and health of workers employed in mines are the concern of ___.
- Which of following is false regarding Monopoly?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)