📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      Ashish and Anil can do a piece of work in 14 days and 20

      days respectively. Ashish completed 45% of the work. Find the time taken by Anil to complete the remaining work.
      A 15 days Correct Answer Incorrect Answer
      B 13 days Correct Answer Incorrect Answer
      C 11 days Correct Answer Incorrect Answer
      D 10 days Correct Answer Incorrect Answer

      Solution

      Let the total work be (LCM of 14 and 20) = 140 units Efficiency of Anil = 140/20 = 7 units/day Remaining work = 140 x 0.55 = 77 units Time taken by Anil to complete the remaining work = 77/7 = 11 days

      Practice Next

      Relevant for Exams:

      ask-question