Question
‘A’ and ‘B’ can complete a certain work in 15 days and 12 days, respectively. They started working together and worked till completion of the work for which they got Rs. 9000 as wage. Find the share of ‘B’ out of total wage.
More ESIC Part B Questions
- Seven people, A, B, C, D, E, F and G, are sitting in a straight row, facing north (not necessarily in the same order). Only 1 person sits to the left of D...
- What does the term ‘Upa’ in the term Upanishad denote?
- The origin of Indian music can be traced to which of the following Vedic Samhitas?
- Time is taken by two trains running in opposite directions to cross a man standing on the platform in 25 seconds and 15 seconds respectively. It took 18 se...
- A @ B' means 'A is the father of B'. 'A % B' means 'A is the wife of B'. 'A $ B' means 'A is the son of B'. 'A & B' means 'A is the sister of B'. If 'P $ Q...
- Which creates an opportunity for the producers to reach beyond the domestic markets?
- If 2 is subtracted from each odd digit and 1 is added to each even digit in the number 83252769, how many digits will occur more than once in the new numbe...
- Legacies are generally
- Bilateral netting sometimes seen in news, it refers to
- Based on the English alphabetical order, three of the following four letter-clusters are alike in a certain way and thus form a group. Which letter-cluster...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)