Question
Working alone, B can complete the work in 16 days. C is
twice as efficient as B and A takes 4 days more than it takes C to complete the work. Working together, in how much time would they be able to complete 13 such works?Solution
Time taken by B to complete the work = 16 days Time taken by C to complete the work = 16/2 = 8 days Time taken by A to complete the work alone = 8 + 4 = 12 days Work done by A, B and C together in 1 day. ⇒ (1/16 + 1/8 + 1/12) = (3 + 6 + 4)/48 = 13/48 this means if would take 48/13 days for A, B and C to complete the work together ∴ Time taken A, B and C to complete 13 works = 13 × 48/13 days = 48 days
A firm budgeted sales of ₹120 lakh but achieved actual sales of ₹100 lakh. Variable cost was budgeted at 60% of sales, and actual cost was 62% of ac...
The process of recording business transactions in a chronological order is called:
Which of the following is not a type of cash book?
The standard time for a task is 4 hours per unit at a wage rate of ₹60 per hour. In a period, 500 units were produced in 1,900 hours, and the actual w...
Under Ind AS 116, a company leases an asset for 5 years. On transition, it recognizes a right-of-use asset and corresponding lease liability. However, t...
In an organization, profit after interest, tax, and dividend on preference shares is 4,00,000. The number of equity shares is 40,000 and the dividend pa...
A claims processing unit uses a mix of clerks and analysts. Budget: 60% clerks (₹200/hr), 40% analysts (₹500/hr) for 10,000 hours. Actual: 55% clerk...
Time of supply means
Company A sold machinery having a WDV of ₹ 40 lakh to Company B for ₹ 50 lakh (FV ₹ 50 lakh) and the same machinery was leased back by Company B T...
A person can hold directorship in ______ companies simultaneously.