Question

    What is the additional provisioning required per quarter

    if DCCO is deferred for non-infrastructure projects? 
    A 0.25% Correct Answer Incorrect Answer
    B 0.50% Correct Answer Incorrect Answer
    C 0.375% Correct Answer Incorrect Answer
    D 0.5625% Correct Answer Incorrect Answer
    E 0.75% Correct Answer Incorrect Answer

    Solution

    For non-infrastructure projects with deferred DCCO, banks must provision an additional 0.5625% per quarter. 

    Practice Next

    Relevant for Exams: