Ms. Sumita Dawra, Secretary of the Ministry of Labour & Employment, inaugurated the 16th Zonal Review Meeting of EPFO. The meeting was also attended by Ms. Neelam Shami Rao, Central Provident Fund Commissioner (CPFC), Shri. Alok Mishra, Joint Secretary of the Ministry of Labor and Employment, and senior officers of EPFO.
Raj, Sanjay and Vaibhav can separately finish a work in 20, 30 and 40 days, respectively. In how many days Raj can finish the work if he is assisted.by ...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
Bittu can finish a task by himself in 60 days, while Anoop and Bittu working together can complete the same task in 28 days. If A...
A and B together can do a piece of work in 30 days, B and C together can do it in 20 days. A starts the work and works on it for 5 days, then B takes it...
A and B together, B and C together and A and C together can complete a piece of work in 80 days, 60 days and 70 days respectively. Find the ratio of the...
If 15 men or 10 boys can finish a task in 18 days, how long will it take for a team of 12 men and 15 boys to complete the same task? (Calculate approxim...
Komal and Seema individually can complete a task in ‘2a’ hours and ‘7a’ hours respectively. If they together can complete half of the work in 7...
A man works twice as efficiently as a woman and three times as efficiently as a child. If 3 men and 4 children can complete a task in 18 days, how long...
If 3 men with 4 boys can earn Rs. 2940 in 7 days and 5 men with 9 boys earn Rs. 4620 in 6 days. In how many days will 5 men with 3 boys earn Rs. 11...
A can complete `1/4` of a work in 6 days and B can complete `2/5` of the work in 12 days. In how many days can both A and B together complete the work?<...