If 36 persons can finish 50% of work in 12 days In how many days 72 person can finish the complete work?
More CSAT GS Questions
- A person is to reach a destination 40 km away. If he covers the first 25 km in 4 hours then at what constant speed should he go so that the average speed f...
- Match List I with List II Choose the correct answer from the options given below:
- The six freedoms in Article 19 can be curtailed by:
- Penicillium is a _____________.
- 8 workers working for 8 days make 8 motor cycles. Then how many motor cycles would be made by 4 workers if they work for 4 days? Assume equal efficiency of...
- New education policy. 2020 is goal to achieve 100% gross enrolment Ratio (GER) in school Education by the year ________.
- Question 7
- Which one of the following bills must be passed by each house of the India parliament separately by special majority?
- How many medals did India win in the London Olympics?
- The substance DDT is now
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)