    • Question

      What is the total investment in Chhattisgarh’s first

      Supercritical Thermal Power Project (SCTPP) in Korba district?
      A ₹10,000 crore Correct Answer Incorrect Answer
      B ₹15,800 crore Correct Answer Incorrect Answer
      C ₹12,500 crore Correct Answer Incorrect Answer
      D ₹14,600 crore Correct Answer Incorrect Answer
      E ₹13,200 crore Correct Answer Incorrect Answer

      Solution

      The SCTPP in Korba district is part of the Hasdeo Thermal Power Station expansion with a total investment of ₹15,800 crore. It will add 1,320 MW capacity to the existing 1,340 MW plant, making energy generation more efficient with lower emissions.