๐Ÿ“ข Too many exams? Donโ€™t know which one suits you best? Book Your Free Expert ๐Ÿ‘‰ call Now!

  • google app store apple app store
  • โœ–

      Question

      What is the total estimated cost of the Namrup IV

      Brownfield Ammonia-Urea Complex?
      A โ‚น9,500 crore Correct Answer Incorrect Answer
      B โ‚น10,000 crore Correct Answer Incorrect Answer
      C โ‚น10,601.40 crore Correct Answer Incorrect Answer
      D โ‚น11,000 crore Correct Answer Incorrect Answer
      E โ‚น12,500 crore Correct Answer Incorrect Answer

      Solution

      The total approved cost for the Namrup IV Fertilizer Plant project is โ‚น10,601.40 crore, with a 70:30 debt-equity ratio. The plant is expected to be completed in 48 months and aims to enhance fertilizer availability in the eastern region.