Question

How many statements about SJVN's Gujrai Solar Power Station is/are incorrect?

1. SJVN Limited commissioned its 50 MW Gujrai Solar Power Station in Uttar Pradesh.

2. The project was executed by SJVN through its renewable arm, SJVN Green Energy Limited (SGEL).

3. The estimated cumulative energy generation over 25 years is 2,477 million units.

A Only 1 Correct Answer Incorrect Answer
B All 3 Correct Answer Incorrect Answer
C Either 1 or 3 Correct Answer Incorrect Answer
D Only 2 Correct Answer Incorrect Answer
E All statements are correct Correct Answer Incorrect Answer

Solution

•     SJVN Limited, a Mini Ratna, Category-I and Schedule ‘A’ Central public sector enterprise under the administrative control of Ministry of Power, Government of India, has begun the successful commercial operation of its 50 MW Gujrai Solar Power Station in Kanpur Dehat, Uttar Pradesh. •     With this milestone, the total installed power capacity of SJVN stands at 2,277 MW, with ten power stations currently operational. •     The 50 MW Gujrai Solar Power Station has been executed by SJVN through its renewable arm, SJVN Green Energy Limited (SGEL) at a cost of Rs. 281 crores. •     The project will generate 107 million units in the first year and the cumulative energy generation over a period of 25 years is estimated to be 2,477 million units. Learn Along: About Uttar Pradesh Chief minister: Yogi Adityanath                   Governor: Anandiben Patel                       Capital: Lucknow

Practice Next

Relevant for Exams:

×
×