>I.                   The Presidential elections are soon to be held in India. These are the 15th Presidential elections. II.                 Presidential elections in India are managed by the Parliament. III.               As per Article 324 of the Constitution of India, an election to fill the vacancy caused by the expiration of the term of office of the outgoing President is required to be completed before the expiration of the term. Which statement/statements is/are incorrect?Solution
The Election Commission announced that the Presidential election would be held on July 18 and counting of votes would be held on July 21 The term of office of Shri Ram Nath Kovind, President of India, is ending on 24th July, 2022. As per Article 62 of the Constitution of India, an election to fill the vacancy caused by the expiration of the term of office of the outgoing President is required to be completed before the expiration of the term. About the Election Commission. Article 324 of the Constitution read with the Presidential and Vice-Presidential Elections Act, 1952, and the Presidential and Vice – Presidential Elections Rules, 1974 vests the superintendence, direction and control of the conduct of election to the office of the President of India in the Election Commission of India. Formed: 25 January 1950                                                   First executive: Sukumar Sen Preceding executive: Sunil Arora                                            Current executive: Sushil Chandra
A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days wi...
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, the...
Ashish and Anil can do a piece of work in 18 days and 24 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete th...
Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20%...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
P and Q together can finish a task in 72 days while Q and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...