24 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 8 hours a day for ...
‘X’ and ‘Y’ are capable of finishing a work in 9 days and 12 days respectively. They worked together for 3 days. Find the number of days ‘Y’...
A man, a woman and a boy can do a work in 4, 8, 32 days respectively. How many boysare required with 1 man and 1 woman to complete the same work in 1/4 ...
30 men can complete a work in 12 days. After 9 days, 15 more men joined them. How many days will they now take to complete the remaining work?
25 men can complete a piece of work in 13 days. One man starts the work and after every day one more man joins the work and this continues till the work...
15 men can complete a piece of work in 5 days, while 20 women can complete it in 5 days. 8 men start working on the job & after working for 3 days, ...
Naina and Kalpana working together can do a piece of work in 10 days, whereas Naina alone can do it in 12 days. In how many days can Kalpana do it alone?
A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to w...
An inlet pipe can fill a tank in 15 minutes when there’s no leakage. However, due to a leak in the tank, it takes 21 minutes to fill it completely. Ho...
Person A can complete a certain task in 20 days, while person B can finish the same task in x days. Together, they can complete the task in 12 days. Det...