Question

The standard labour cost is based on 500 hours at ₹2.20 per hour. The actual labour used is 475 hours at ₹2.00 per hour. What is the Labour Rate Variance?

A ₹95 (Favourable)
B ₹110 (Favourable)
C ₹95 (Adverse)
D ₹110 (Adverse)
E ₹100 (Favourable)