    Question

    In the life cycle of a project under project finance, at

    the end of which stage are scope stability, resource mobilization, and detailed work schedules defined?
    A Execution Stage Correct Answer Incorrect Answer
    B Monitoring Stage Correct Answer Incorrect Answer
    C Planning Stage Correct Answer Incorrect Answer
    D Closure Stage Correct Answer Incorrect Answer
    E Initiation Stage Correct Answer Incorrect Answer

    Solution

    The planning stage finalizes the scope, timelines, and resources, setting the foundation for execution.