A government is looking to undertake a large infrastructure project, such as the construction of a new highway. However, the government has limited financial resources and expertise in managing such projects. To overcome these challenges, the government is considering partnering with a private entity to design, build, finance, and operate the highway. Which type of Public-Private Partnership (PP

  • P model would be most appropriate for this project, considering the government's objectives and constraints?
A Build-Operate-Transfer (BOT)
B Build-Own-Operate (BOO)
C Build-Lease-Transfer (BLT)
D Design-Build (DB)
E Operate-Maintain-Transfer (OMT)