Question
Which of the following is not one of the pillars of
Basel III?Solution
The three pillars as given by Basel accords are: •First Pillar: Minimum Capital Requirement - The first pillar Minimum Capital Requirement is mainly for total risk including the credit risk, market risk as well as Operational Risk. •Second Pillar: Supervisory Review Process is basically intended to ensure that the banks have adequate capital to support all the risks associated in their businesses. As per RBI guidelines ICAAP or Internal Capital Adequacy Assessment Process is done by banks themselves while SREP or Supervisory Review and Evaluation Process is conducted by RBI. •Third Pillar: Market Discipline - The idea of the third pillar is to complement the first and second pillar. This is basically a discipline followed by the bank such as disclosing its capital structure, tier-I and Tier –II Capital and approaches to assess the capital adequacy.
‘A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in ...
It is given that 40% of the work completed by Lokesh is equal to 30% of the work completed by Meena. If Lokesh alone can complete the entire work in 28 ...
A person travelled for the first 150 km at a certain speed in 6 hours. After that, the speed of the person decreased by 6 km/h. If the person took a tot...
A work can be completed by ‘A’ and ‘B’, alone in 15 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the sam...
A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 25 days. Find the time taken by B to compl...
A is five times as efficient as B and can finish a piece of work in 36 days less than B. B can finish this work in how many days?
P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &l...
In a retreat, there is sufficient food for 300 people for the duration of the retreat. After 8 days, 100 people leave the retreat. Then, after another 3...
A2 type ‘P’ pipes can fill a tank in 350 hours, while B2 type ‘Q’ pipes can fill the same tank in 504 hours. (10A × 6B) t...
‘A’ alone can do some work in 12 days. ‘B’ and ‘C’ together can do the same work in 6 days. If ‘B’ is half as efficient as ‘A’, then...