Question
A project management technique which uses time as the
variable is known asSolution
PERT is an acronym for Program (Project) Evaluation and Review Technique, in which planning, scheduling, organising, coordinating and controlling of certain activities take place. The technique studies and represents the tasks undertaken to complete a project, to identify the least time for completing a task and the minimum time required to complete the whole project.
A merchant has 1200 kg of sugar, part of which he sells at 9% profit and the rest at 15% profit. He gains 11% on the whole. The quantity (in kg) sold at...
A car travel 20km/h for 30 min and at x km/h for 45 min. If the average speed of the car for entire journey is 14 km/h find the value of x.
βAβ and βBβ can do a piece of work in 25 days and 30 days, respectively. If they started the work together and worked on it for 5 days, then fin...
In what ratio coffee at 325 Rs/kg should be mixed with the coffee at 375 Rs/kg so that after mixture its rate become 340 Rs/kg if the quantity of 1st ty...
In what ratio rice at 44 Rs/kg should be mixed with the rice at 28 Rs/kg so that selling mixture at Rs 42 per kg gives the profit of 20% if the quantity...
A car travel 20km/h for 30 min and at x km/h for 45 min. If the average speed of the car for entire journey is 14 km/h find the value of x.
Cost of two types of pulses is Rs.25 and Rs, 30 per kg, respectively. If both the pulses are mixed together in the ratio 2:3, then what should be the pr...
12, 13, 22, 47, 96, ?
There are two buckets X and Y containing mixture of milk and water in which concentration of milk is (a-9)% and (a+15)%, respectively. They are mixed to...
The ratio of liquor and soda in a mixture of 50 liters is 3:2. How much soda should be mixed to make the ratio 6:7?