Question

Which of the following is a contingent credit line sanctioned for the project at the time of financial closure to fund any cost overrun during the construction phase of the project?

A Working capital Term Loan (WCTL)
B Standby credit facility (SBCF)
C Line of Credit (LoC)
D Letter of Credit (LC)
E Bank Guarantee (BG)