    Question

    What is the maximum assistance provided for

    Infrastructure Development under MSE-CDP?  
    A ₹10 crore Correct Answer Incorrect Answer
    B ₹13.5 crore Correct Answer Incorrect Answer
    C ₹15 crore Correct Answer Incorrect Answer
    D ₹20 crore Correct Answer Incorrect Answer
    E ₹30 crore Correct Answer Incorrect Answer

    Solution

    Under MSE-CDP, up to 70% of the maximum project cost of ₹15 crore is provided as assistance for Infrastructure Development.  