Start learning 50% faster. Sign in now
Explanation: Had completed (correct tense): In this context, the past perfect tense "had completed" is appropriate as it indicates that the completion of Jack's homework occurred before another past action (the teacher arriving). Options: (a) Completed: This is the past tense, but it doesn't convey the necessary chronological sequence of events. It suggests completion without specifying its relationship to the teacher's arrival. (b) Complete: This is the base form of the verb and does not convey the correct past tense. (c) Completes: This is the present simple tense and is not suitable for describing a completed action before another past action. (d) Had completed: This is the correct past perfect tense, indicating that the homework was finished before the teacher arrived.
Amit, Bheema, and Chetna can finish the task in 32 days, 24 days, and 30 days respectively. If they start the task together, and ...
‘A’ and ‘B’ can do a piece of work in 20 days and 25 days, respectively. If they started the work together and worked on it for 4 days, then fin...
A man takes 200 days to finish a work alone. If he started working alone and joined by one more man having same efficiency as of him every day from 2nd ...
A team of 40 men is assigned to finish a project within 24 days. They began the task simultaneously. To complete the project 6 days ahead of the planned...
A alone work for 6 days then left the work and B alone finishes remaining work in 12 days. If ratio of time taken by A alone to B alone to finish work ...
A contractor hired 40 workers to complete a work in 100 days. After 70 days, it was found that only 2/5th of the work was completed. Find the number of ...
‘A’ and ‘B’ can do a piece of work in 20 days and 30 days, respectively. If they started the work together and worked on it for 7 days, then fin...
Aarif, Arun, and Abraham can do work in 12, 15, and 24 days, respectively. They all begin together. Aarif leaves the work 1 day, Arun 3 days and Abraham...
Ajay, Bablu and Chirag can complete a certain work in 21, 28 and 15 days respectively. Ajay and Chirag started the work while Bablu joined them after ...
Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish t...