P and Q together can do a job in 6 days, Q & R can finish the same work in 60/7 days. P started the work and worked for 3 days. Q & R continued ...
X, Y and E can do piece of work in 24, 30 and 40 days respectively. All three began to work together but X and Y left 6 and 8 days respectively before c...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 60% of the ...
Aarif, Arun, and Abraham can do work in 12, 15, and 24 days, respectively. They all begin together. Aarif leaves the work 1 day, Arun 3 days and Abraham...
A and B together can complete a piece of work in 48 days while B and C together can complete the same work in 58 days. All of three together can complet...
P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &l...
‘A’ alone can complete a work in 15 days while ‘A’ and ‘B’ together can complete the same work in 10 days. How much percentage of the work, ...
Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 18 days to complete 40% of the work. If the efficiency of Sachin is 25%...
Veer can complete a work in X days and Ayush is 40% more efficient than Veer. If both complete 4/7th of work together and get Rs. 1200 for it...
P’s 3 days work is equal to Q’s 4 days work. If P and Q together can complete the work in 32 days then how much time Q will take to complete 75% of ...