Question
The President the aspirations of the Scheduled Castes
and the Scheduled Tribes/(P) with political parties, industry and other bodies/(Q) revealed that the Government would initiate a dialogue/(R) on how best the private sector could fulfill/(S). The correct sequence should be: Directions : In the following items some parts of the sentence have been jumbled up. You are required to re-arrange these parts which are labelled P, Q. R and S to produce the correct sentence. Choose the proper sequence and mark in your Answer Sheet accordingly.Solution
The correct sequence of the sentence is R-Q-S-P. Therefore, option (b) is the correct answer. The sentence should start with The President ‘revealed’ which is given in R, so R should come first after rearrangement, followed by Q as it mentions the dialogue ‘with political parties’. Q should be followed by S-P as it makes the sentence correct in meaning. The correct sequence after rearrangement is RQSP which is given in option (b). Hence, option (b) is the right answer.
Work efficiency of Chacha and Bhatija are in the ratio of 3 : 1. They working together to do a piece of work and completed the work in 24 days. Now in h...
A and B can complete a task in 63 days and 42 days, respectively. If C is 40% more efficient than the combined efficiency of A and B, how much time will...
15 men can complete a piece of work in 5 days, while 20 women can complete it in 5 days. 8 men start working on the job & after working for 3 days, all...
‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest o...
Three pipes A, B and C can fill/empty a tank. A can fill it in 12 hours, B in 15 hours, and C can empty a full tank in 20 hours. All three pipes are ope...
A can complete a work in 12 days and B can complete the same work in 18 days. A works alone for 4 days and then B alone finishes the remaining work. In ...
A can finish a piece of work in 12 days and B can finish it in 20 days. If they work together, in how many days will they finish the work?
P can complete a job in 30 days. Q alone can complete the same job in 20 days. P works for 18 days and then the remaining job is completed by Q. How man...
P’s 2 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 30 days then how much time Q will take to complete 60% of ...
Working 10 hours a day, Jagan can complete a work in 12 days while working 8 hours a day, Magan can complete the same work in 9 days. If Jagan and Magan...