Start learning 50% faster. Sign in now
Get Started with ixamBee
Start learning 50% faster. Sign in nowThe correct sequence is Q-P-S-R, which is given in option (c). Therefore, option (c) is the correct answer. The second statement after S1 should be Q as S talks about the worst man-made catastrophes and Q talks about what happened there exactly. P should be the following statement after Q as it tells us that what happened after the catastrophe. S should come after P because it tells about the rest of the population who survived. R should follow S as it gives the reason that why the disaster happened.
Sam alone can complete a work in 60 days. Arun is three times as efficient as Sam. Find the percentage of work completed by Sam and Arun together in 15 ...
55 men can complete a piece of work in 18 days. ‘x’ men started the work and after 9 days 64 more men joined them so that whole work was finished in...
A certain Sales target was assigned to a team of men to complete in 18 days. But 8 men did not turn up for the target and the rest men complete the sale...
A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after whic...
Team A can built a project in 6 hours less than the time taken by Team B to built the same project.
The ratio of the strength of Team A to that o...
35 typists working 9 hours per day can complete a typing job in 14 days. ____ typists working _____ hours per day can complete (3/4)th part of the work ...
'Y' is 36% less efficient compared to 'X'. If 'X' requires 86.4 days to finish a task, determine how many days 'Y' will take to complete the same task.
Q can complete a project in ‘x ‘ hours , R needs ‘0.7x’ hours to do half of The same project. R and S jointly can complete the same project in 1...
A and B together can do a work in 8 days. If A can alone do the same work in 24 days, then in how many days B alone will do the same work?