A and B are capable of completing a project individually in 40 days and 50 days, respectively. Initially, A and B collaborated on the project, and after...
25 men can complete a piece of work in 30 days. βxβ men started the work and after 24 days 60 more men joined them so that whole work was finished i...
- Raj alone can complete a work in 25 days. Mohan is five times as efficient as Raj. Find the percentage of work completed by Raj and Mohan together in 5 day...
- If βXβ finishes a project in 24 days whereas βXβ and βYβ working together can finish it in 15 days, then determine the time βYβ alone will ...
'Sumit' can complete (3/8) of a job in 24 days, where as 'Sumit' and 'Tarun' together can finish it in 16 days. Calculate the time 'Tarun' needs to comp...
It is given that 40% of the work completed by Lokesh is equal to 30% of the work completed by Meena. If Lokesh alone can complete the entire work in 28 ...
Worker βPβ can complete a job in 30 days, and together with βQβ, they can finish it in 12 days. If βQβ worked alone for 15 days and then sto...
A and B can do a work in 24 days and 32 days, respectively. If A works on it for βxβ days and B works on it for βx β 1β days, then one-third o...
A tank is filled by three pipes with uniform flow. The first two pipes operating simultaneously fill the tank in the same time during which the tank is ...
A, B, and C together can do a piece of work in 28 days, whereas C alone can do the same work in 42 days. How long will A and B take together to finish it?