'P' is 25% less efficient than 'Q'. 'Q' takes 20 days less
than 'P' to complete the same task. Find how much time 'Q' will take to complete the work if he works at 75% of his efficiency.Solution
ATQ,
Let the efficiency of 'Q' be '10x' units/day
So, efficiency of 'P' = 10x × 0.75 = '7.5x' units/day
So, ratio of efficiency of time taken by 'P' and 'Q' = 10x : 7.5x = 4 : 3
Let time taken by 'P' and 'Q' be '4y' days and '3y' days
So, 4y - 3y = 20
So, y = 20
Time taken by Q to finish the work = 3 × 20 = 60 days
So, required time = 60 ÷ 0.75 = 80 days
During hard market conditions, insurers tend to raise premiums and restrict coverage due to past underwriting losses. What phase does this describe in t...
Which of the following statement is incorrect with respect to Valuation of Inventories?
What is the loan amount and tenure under the second tranche of finance provided through PM Vishwakarma Scheme?
In a computerized information processing cycle, which component involves saving data for future use?Â
If an MSME moves to a higher category due to reclassification, for how many years can it continue to avail benefits of the previous category (non-tax be...
In insurance accounting, what does the "claims reserve" represent?
Which function in MS Excel is used to find the present value of an investment?
In an organization, profit after interest, tax, and dividend on preference shares is 4,00,000. The number of equity shares is 40,000 and the dividend pa...
Which of the following reduces working capital requirement?
If ₹10,000 is invested at 10% p.a. compounded annually, what will be the amount after 2 years?