Question
'P' is 25% less efficient than 'Q'. 'Q' takes 20 days less
than 'P' to complete the same task. Find how much time 'Q' will take to complete the work if he works at 75% of his efficiency.Solution
ATQ,
Let the efficiency of 'Q' be '10x' units/day
So, efficiency of 'P' = 10x × 0.75 = '7.5x' units/day
So, ratio of efficiency of time taken by 'P' and 'Q' = 10x : 7.5x = 4 : 3
Let time taken by 'P' and 'Q' be '4y' days and '3y' days
So, 4y - 3y = 20
So, y = 20
Time taken by Q to finish the work = 3 × 20 = 60 days
So, required time = 60 ÷ 0.75 = 80 days
It was held that the dying declaration made through signs, gestures or by nods are admissible as evidence, in the case of?
People who are not liable under the Indian Penal Code when working in their official capacities?
Under the Civil Procedure Code (CPC) in India, which provision deals with the power of the court to issue a temporary injunction?
Section 111 of the Evidence Act speaks of such situations where one person stands in a position of ………… to the other person
What does JECFA stands for?
In every plaint, facts shall be proved by affidavit . Provided that such an affidavit shall be in the form and manner as prescribed under Order VI of r...
Which of the following best represents a core principle of natural justice in administrative law?
A person shall be deemed to be dead if he remained unheard for_______years.Â
Which of the following is not a ground on which a Data Principal may withdraw consent under the Digital Personal Data Protection Act, 2023?
In 2023 who was appointed as the new Chief Justice of India?