Question
'P' is 25% less efficient than 'Q'. 'Q' takes 20 days less than 'P' to complete the same task. Find how much time 'Q' will take to complete the work if he works at 75% of his efficiency.
More Difficult level Section Tests Questions
- Find the simplified value of the given expression.
- Find the greatest 3-digit number which when divided by 11 or 16 leaves 3 as remainder.
- Ritesh got 84 marks in an exam, which is 100% more than the marks secured by Mohan. If Mohan failed the exam by 4 marks, then find the total marks of Rites...
- The volumes of two hemispheres are in the ratio 1000:3375. Determine the ratio of their total surface areas. (Take π = 22/7)
- A boat’s speed in still water is to the stream’s speed as 7:2. If the boat covers 50.4 km downstream in 96 minutes, find its upstream speed.
- P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 day...
- The ratio of M to N is 4:9, and that of N to O is 3:2. If the difference between O and M is 60, what is the total of M, N, and O?
- Ravi invested Rs. 10,200 at 20% p.a. for 2 years and Rs. 11,500 at 28% p.a. for 2 years on simple interest. What is the total interest he earned?
- The ratio of the radii of the bases of a cylinder and a cone is 2:3, while the ratio of their heights is 3:5. What is the ratio of the volume of the cylind...
- Ravi sold 80 notebooks and made a profit equal to the cost price of 5 notebooks. What is the percentage of profit he made?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt