Question

'P' is 25% less efficient than 'Q'. 'Q' takes 20 days less than 'P' to complete the same task. Find how much time 'Q' will take to complete the work if he works at 75% of his efficiency.

A 50 days
B 28 days
C 80 days
D 65 days