Question
Two workers, A and B, can finish a task in 36 days and 48
days respectively, working alone. How many days will they take to complete the work together?Solution
ATQ,
Let the total work be 144 units (LCM of 36 and 48)
Efficiency of 'A' = (144 ÷ 36) = 4 units/day
Efficiency of 'B' = (144 ÷ 48) = 3 units/day
Required time = 144 ÷ (4 + 3) = (144 ÷ 7) = 20(4/7) days
Select the related word/letters/number from the given alternatives.
42 : 14 :: 32 : (?)
Select the odd group of numbers. (NOTE: Operations should be performed on the whole numbers, without breaking down the numbers into its constituent digi...
Statements:
X < W ≤ F = Q ≥ P = T ≥O ≥ S = R
Conclusions:
I) Q > R
I) Q = R
Select the option in which the numbers are not related in the same way as are the number of the following set.
(520, 8, 56)
Select the combination of letters that when sequentially placed in the blanks of the given series will complete the series.
F S_ Y Z _ _ N _Z F _ _ Y Z
Select the option that is related to fourth number in the same way as the first number is related to the second number and the fifth number is related t...
- Select the option that is related to the fifth letter-cluster in the same way as the second letter-cluster is related to the first letter-cluster and the f...
- Select the option that is related to the third term in the same way as the second term is related to first term and the sixth term is related to the fifth ...
Who sits adjacent to S?
In a family, there are seven persons, comprising two married couple, S is the only child of N and the granddaughter of L. N is a widow. N and Q are sist...