πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    ⚑ Month End Offer - Flat 52% Off On All Courses! Enroll Now ⚑
    00:00:00 AM Left

    Question

    A firm evaluating two mutually exclusive projects uses

    NPV and IRR. Project A has higher NPV but lower IRR than Project B. Which project should be selected and why?
    A Project A, due to higher IRR Correct Answer Incorrect Answer
    B Project B, due to lower NPV risk Correct Answer Incorrect Answer
    C Project A, due to higher wealth creation Correct Answer Incorrect Answer
    D Project B, IRR is a better measure Correct Answer Incorrect Answer

    Solution

    NPV directly measures value addition. For mutually exclusive projects, higher NPV is preferred even if IRR is lower.

    Practice Next
    More Capital Budgeting Questions
    ask-question